UAE · Revit modeling · MEP coordination · Clash detection

BIM Services in the UAE

Optimar Precon builds Revit models, MEP coordination models and clash reports for main contractors, MEP subcontractors and consultants across the UAE, delivered to your BIM execution plan and coordination schedule.

  • Architectural, structural and MEP models in Revit, from LOD 300 to LOD 400
  • Federated clash detection in Navisworks, with issue reports ready for each coordination meeting
  • Team 1.5 hours ahead of UAE time, so we join your coordination meetings live

Get a UAE BIM Quote

Share drawings, Revit or IFC models and your BEP, plus the next coordination milestone. We reply with scope, fee and delivery date.

29+Years of group experience
3,270+Projects completed
1,268Issues resolved on one data centre job
1.5 hAhead of UAE time
Why UAE teams outsource BIM to us

BIM Capacity for Fast-Track UAE Projects

Towers, hospitals and data centres in the UAE pack dense MEP into tight ceiling zones, often on compressed programmes. We add modelers and coordinators when your own BIM team is stretched, working inside your models and standards.

BEP

Your BEP and standards

We follow your BIM execution plan, templates, shared coordinates and ISO 19650 file naming from the first model issue.

MEP

Strong on building services

Chilled water, ductwork, cable trays, drainage and fire fighting, coordinated in plant rooms, risers and ceiling voids.

1.5h

Live in your coordination meetings

India is 1.5 hours ahead of the UAE, so clash reviews and model updates happen during your working week.

Federated BIM model showing architectural, structural and MEP systems for a UAE building
What we deliver

BIM Services for UAE Projects

Order one discipline or a full coordination package. Each service links to more detail.

Architectural and structural BIM

Revit models of walls, floors, ceilings, facades, concrete and steel, built from approved design drawings to the agreed LOD.

BIM modeling →

MEP BIM modeling

HVAC, chilled water, electrical, plumbing, drainage and fire fighting, modeled with real equipment sizes and access zones.

MEP BIM →

BIM coordination

Federated models, weekly coordination cycles and an issue register that the main contractor and trades work from.

BIM coordination →

Clash detection

Navisworks clash tests filtered into real issues, grouped by zone and trade, and issued as viewpoints or BCF files.

Clash detection →

CAD to BIM

2D CAD and PDF drawing sets turned into editable Revit models for design development, coordination or refurbishment.

CAD to BIM →

Scan to BIM

Existing buildings modeled from your laser-scan point clouds, for retrofits, fit-outs and facility records.

Point cloud to BIM →
Tools we use: RevitNavisworksAutodesk Construction CloudTekla StructuresIFC / BCF
Built for UAE projects

Models Set Up the Way UAE Projects Require

What UAE clients, consultants and main contractors usually ask for in a BIM scope, and how we handle it.

Authority BIM submissions

Dubai Municipality requires BIM for larger and specialist buildings. We prepare models to your consultant’s submission requirements.

ISO 19650 and EIRs

Many UAE developers and government clients write ISO 19650 into their information requirements. We follow the naming, status codes and exchange rules in your EIR and BEP.

Right LOD for the job

LOD 300 for design coordination, LOD 350 where trades need connections and supports, and LOD 400 only where a model is used for fabrication.

Handover data

Asset parameters and COBie-style data for developers and facility managers, when it’s included in the scope.

Open exchanges

Native RVT plus IFC exports and BCF issue files, so consultants and trades on other platforms can still take part.

Model QA before every issue

Shared coordinates, levels, worksets, parameters and file naming are checked before each model goes out.

We build and coordinate models from your design information. Design decisions, engineering checks and authority approvals stay with the appointed consultants.

Proof and example scopes

How We Run MEP Coordination

A documented data centre coordination programme, and three typical UAE BIM packages.

MEP clash detection for a hyperscale data centre fit-out
Success story · Hyperscale data centre · US

1,268 MEP issues resolved before construction release

On a 24 MW data centre fit-out with two data halls and six electrical rooms, five trade models had no single coordinator. We ran an 11-week federated programme with weekly clash cycles. The first run showed 9,847 raw clashes, which we filtered into 1,412 real issues and tracked to closure. UAE data centre and hospital projects face the same density.

11 wksTo construction release
1,268Issues resolved in model
68Slab penetrations fixed before pour
Read the case study →
Example scope · Dubai tower

MEP coordination for typical tower floors

A main contractor needs trade models federated and clash-checked floor by floor ahead of each pour cycle.

You send
Trade models, BEP, programme
You get
Weekly clash reports, issue register
Typical time
First report in 1–2 weeks, then weekly
Example scope · Abu Dhabi hospital

CAD to BIM for a refurbishment wing

A contractor has only 2D drawings of an existing wing and needs a Revit model to plan new MEP routes.

You send
As-built CAD, survey notes
You get
Architectural and MEP Revit model
Typical time
3–4 weeks
Example scope · Sharjah warehouse

Structural and MEP model at LOD 300

A design-and-build contractor needs a coordinated model of a steel warehouse for design review and quantities.

You send
Structural and MEP drawings
You get
Coordinated RVT plus IFC, clash report
Typical time
2–3 weeks

The three packages are example scopes, not client case studies. Your quote is based on your own models and drawings. See more in our success stories, including our ISO 19650 university project.

How we work

From BEP to Coordinated Models

Scope and BEP review

We review your models, drawings and BEP, then confirm disciplines, LOD, fee and milestones.

Model setup

We set up shared coordinates, templates, worksets and file naming before any modeling starts.

Model and federate

We model each discipline, then combine them in Navisworks. Anything unclear in the design goes back to you as an RFI.

Clash cycles and issue

Weekly clash runs, filtered issue reports and checked model issues, timed to your coordination meetings.

FAQs

Questions UAE Teams Ask About BIM

Will you work to our BIM execution plan and ISO 19650 requirements?

Yes. We follow your BEP, templates, shared coordinates and the naming, status and exchange rules in your information requirements, including ISO 19650 conventions where the client specifies them.

Which LOD do you model to?

Usually LOD 300 for design coordination and LOD 350 where trades need connections, supports and clearances. We model to LOD 400 only when the model will be used for fabrication and the inputs support it.

Can you join our weekly coordination meetings?

Yes. Our team is 1.5 hours ahead of the UAE, so we join meetings live during your working day, present clash reports and update the models straight after. You can also reach us on WhatsApp at +91 88008 75774.

Can you prepare models for a Dubai Municipality BIM submission?

Yes. We build and check the models to your consultant’s submission requirements. The submission itself and design responsibility stay with the appointed consultant.

How is BIM work priced?

As a fixed fee per modeling package, based on area, disciplines, LOD and deadline. For ongoing coordination, you can hire a dedicated BIM modeler or coordinator on a monthly basis.

Coordination Meeting Coming Up?

Send the models, BEP and your next milestone. You’ll get a scope, a fixed fee and a delivery date, usually the same working day.