SUCCESS STORY
Clash Detection   |   Confidential Hyperscale Fit Out   |   United States

Data Center MEP Clash Detection(US Hyperscale Fit-Out)

MEP Clash Detection Resolved 1,268 Coordination Issues Before Slab Pour on a 24 MW Hyperscale Fit Out
Summary

Optimar Precon ran the MEP coordination programme for a Phase 1 hyperscale data center fit out covering two data halls and six electrical rooms. Across an 11 week programme, a federated model review surfaced 9,847 raw hard clashes, which were filtered and grouped into 1,412 valid coordination issues. Of these, 1,268 were resolved inside the model before construction release, and 68 were slab penetration conflicts closed before concrete was placed.

Data center MEP coordination above server racks

Confidential hyperscale operator
24 MW Phase 1 fit out
11 week coordination programme
1,412 issues tracked to closure
68 penetrations resolved pre pour

LIVE COORDINATION PROGRAMME · CONSTRUCTION RELEASE PROTECTED
11Weeksfrom model handover to construction release sign off

Three coordination sprints, weekly clash cycles, 48 hour issue reporting

9,847Raw hard clasheson first federated run
1,412Valid coordination issuesafter rule filtering
1,268Issues resolvedin model before release
68Slab penetrations resolvedbefore pour

Project overview

MEP Coordination for Two Data Halls and Six Electrical Rooms

The operator was delivering Phase 1 of a multi phase campus. Two data halls totalling 78,000 sq ft of white space were being fitted out concurrently with the six electrical rooms serving them. Mechanical, electrical, plumbing, fire protection and containment packages had each been modelled by separate trade contractors to LOD 350, but no single party held responsibility for federated coordination across all five.

Client
Confidential hyperscale operator
Project stage
Phase 1 fit out, pre construction release
Programme
11 weeks, three coordination sprints
Critical load
24 MW across two data halls
Disciplines
Mechanical, electrical, plumbing, fire protection, containment, structural interface
Model maturity
LOD 350 trade models, federated for coordination

Data hall with coordinated MEP and containment systems

Project brief

A Single Coordination Authority Across Five Trade Models

Each trade contractor had modelled its own scope competently. The problem was the space between them. The mechanical contractor’s chilled water routing, the electrical contractor’s busway runs, the containment subcontractor’s cable tray levels and the fire protection contractor’s pre action mains were each internally clean and mutually incompatible in the overhead zone.

The operator needed:
  • ✅ One federated model maintained across all five trade packages
  • ✅ A filtered, deduplicated issue register rather than a raw clash dump
  • ✅ Weekly coordination cycles that trade contractors could actually action
  • ✅ Structural penetration and sleeve conflicts identified before slab pour
  • ✅ Design queries escalated with a clear owner and a decision deadline
  • ✅ A construction release position naming every unresolved item explicitly
Mission critical BIM coordination review

Optimar Precon assignment

Federated Model Management, Rule Based Clash Testing and Issue Closure Tracking

Through our clash detection services and data center preconstruction services, Optimar Precon acted as the single coordination authority across the trade models while design responsibility remained with the project’s engineers of record.

01

Model federation

Assemble trade models on a shared coordinate system and validate origin, units, level datums and naming against the project BIM execution plan.

02

Rule based clash testing

Configure discipline pair clash tests with tolerances appropriate to each combination, then filter and group results into unique, actionable issues instead of reporting raw hit counts.

03

Coordination sprints

Run weekly cycles: test, group, assign, review in coordination session, verify closure in the following run.

04

Escalation and release control

Route issues requiring design intervention to the engineer of record with a documented decision deadline, and produce a construction release status listing every open item.

◎ Primary project objectiveReach construction release on the overhead MEP and containment zone with every conflict either resolved in the model or explicitly named as an open item with a named owner. The operator needed to know what had been tested, what had been closed, what remained open, and who held the next decision.

The coordination challenge

Congestion Was Not Evenly Distributed

Electrical room density in a mission critical data center

Risk 01

Electrical room density

The six electrical rooms occupied a small fraction of the coordinated floor area but concentrated switchgear, UPS modules, PDUs, battery cabinets, containment risers, and the mechanical and fire protection services serving them. Available overhead volume was minimal and access clearance requirements were non negotiable.

BIM coordination of structural interfaces and building services

Risk 02

Sequence locked structural interfaces

Slab penetrations, sleeves and cast in supports had to be positioned before pour. Any conflict discovered after concrete placement converts from a modelling correction into core drilling through a structural element, with engineering approval, scanning and programme impact attached.

High density MEP coordination and clearance review in a data center

Risk 03

Clearance conflicts that pass a clash test

Hard clash detection finds intersecting geometry. It does not find a cable tray at the correct elevation blocking a switchgear arc flash access zone, or a valve positioned where a battery cabinet door needs to swing. These require rule sets built around maintenance and code clearance, not geometry alone.

Congestion analysis

Six Electrical Rooms Held 43% of All Coordination Issues

Once raw clashes were grouped into valid issues, distribution showed where coordination effort actually needed to go.

1,412 valid issues total604 inside electrical rooms (43%)808 across white space, corridors and service risers
1,412Valid Issues
57%Across white space, corridors and service risers (808 issues)
43%Inside electrical rooms (604 issues)
Issue category Count
Overhead containment vs chilled water piping 213
Busway routing vs cable tray levels 187
Pre action fire main vs containment and lighting 156
Electrical room access and maintenance clearance 118
Structural penetrations, sleeves and cast in supports 68
Hanger, support and seismic bracing conflicts 142
Remaining single trade and miscellaneous issues 528

Coordination priority sequence

01

Structural interface first

Anything affecting slab, penetration or cast in items was prioritised regardless of severity, because the closure window was fixed by the pour date.

02

Busway and containment levels second

Agreeing a stacked elevation strategy removed a large share of downstream conflicts before resolving them individually.

03

Clearance zones third

Arc flash boundaries, cabinet door swings, equipment pull space and maintenance access were modelled as solids and tested as clash geometry.

04

Everything else fourth

Remaining issues were assigned on a weekly cycle with closure verified in the following clash run.

The coordination solution

Three Sprints, Weekly Cycles, One Issue Register

Sprint 1Weeks 1 to 4
Sprint 2Weeks 5 to 8
Sprint 3Weeks 9 to 11

Federated model validated. Full clash test executed. Penetration and cast in conflicts isolated and driven to closure ahead of the pour sequence. Busway and containment elevation strategy agreed across trades.

The 604 electrical room issues worked through in room by room coordination sessions, with clearance zones modelled as testable geometry.

Remaining white space and riser issues resolved. Open items escalated with decision deadlines. Construction release status package issued.

Weekly cycle within each sprint:

Trade model updates received
Federated model rebuilt and clash tests re run
New and unresolved issues grouped and assigned
Issue report issued within 48 hours
Coordination session held
Closure verified in the following run

Escalation control

144 Issues Required Design Intervention

Not every conflict can be resolved by moving something. Where two systems both had a legitimate claim to the same space, or where a resolution would breach a design parameter, the issue was escalated rather than absorbed.

144escalated to engineer of record
113resolved by clarification or confirmation of design intent
31required a design change

Each escalation carried the affected trades, the space constraint, the options considered, the reason no coordination level resolution existed, and a decision deadline tied to the construction sequence.

Quality control

Five Checks Before Any Issue Was Marked Closed

01Geometry check

Confirm the conflict resolved rather than displaced into a new one.

02Clearance check

Verify maintenance, access and code clearance envelopes remain intact after the move.

03Support check

Confirm hangers, supports and bracing were relocated with the service, not left orphaned.

04Discipline sign off

Affected trade contractor confirms the resolution is buildable within its scope.

05Register check

Issue status, owner and closure evidence recorded before the item leaves the active register.

Reported project outcomes

Coordination Closed Before Concrete, Not After

Model resolution — 1,268 issues

Resolved in model before construction release. 89.8% of all valid coordination issues closed without field intervention.

Structural interface — 68 penetrations

Resolved before slab pour, including 22 conflicts that would have required core drilling through reinforced slab, with attendant scanning, engineering approval and programme impact.

RFI avoidance — approximately 211 RFIs

Estimated field RFIs avoided, applying a conservative one in six conversion assumption to the 1,268 model resolved issues. At an average RFI processing cost of roughly $1,080, this represents approximately $228,000 in avoided RFI administration alone, separate from any construction cost impact.

Field rework — approximately 1,850 hours

Estimated trade labour hours avoided, derived from the 68 pre pour penetration resolutions and 142 support and bracing conflicts closed in model.

Positional accuracy — 96.4%

Spot verified model to field match. Overhead installations checked during construction matched coordinated model positions within project tolerance.

Programme — 9 working days

Protected on the containment install sequence. The containment package started on the planned date rather than waiting on penetration resolution.

Before and after

Before Optimar Precon’s coordination programme

  • Five competent trade models with no federated owner
  • Raw clash counts in the thousands with no filtering
  • No agreed busway and containment elevation strategy
  • Penetration conflicts unidentified with the pour date approaching
  • Clearance and access conflicts invisible to hard clash testing
  • No single issue register or closure evidence

After the 11 week programme

  • One federated model maintained across all five packages
  • 1,412 valid issues tracked individually to closure
  • Stacked elevation strategy agreed and modelled
  • 68 penetrations resolved ahead of pour
  • Clearance zones modelled as testable geometry
  • Construction release issued with every open item named and owned

Project deliverables
01Federated coordination model

Maintained across five trade packages on a validated shared coordinate system.

02Clash test configuration and rule sets

Discipline pair tests with documented tolerances, reusable on subsequent phases.

03Weekly issue reports

Grouped, assigned, deduplicated issues with 48 hour turnaround from each clash run.

04Issue register with closure evidence

All 1,412 items with status, owner, resolution and verification record.

05Penetration and sleeve schedule

Coordinated locations issued to the structural package ahead of pour.

06Escalation log

144 design queries with options, constraints and decision deadlines.

07Construction release status package

Closed items, open items, owners and outstanding decisions at release.

08Coordination session records

Attendance, decisions and actions from each weekly session.

What made delivery effective
Filtered issues, not raw counts

9,847 raw clashes would have been ignored by trade contractors. 1,412 grouped, assigned issues got actioned.

Sequence driven priority

Structural interface items were worked first because their closure window was fixed by construction, not by severity ranking.

Clearance modelled as geometry

Access and code clearance envelopes were made testable rather than left to visual review.

Escalation with deadlines

Design queries carried decision dates tied to the construction sequence, so open items did not drift into the field.

Named open items at release

Construction release did not claim zero conflicts. It named every remaining one with an owner.

Confidentiality and responsibility

Commercially sensitive project details have been withheld

The operator’s name, campus identity, project location, capacity roadmap, contract value and commercial terms have not been published.

Responsibility clarification: Design responsibility, engineering approval, code compliance, structural adequacy, equipment selection, procurement, installation workmanship and construction means and methods remained with the project’s engineers of record, trade contractors and construction manager throughout. Optimar Precon’s scope was federated model coordination, clash testing, issue tracking and escalation reporting. RFI avoidance and rework hour figures are estimates derived from resolved issue counts and published industry cost benchmarks; they are not audited project savings. Results on other projects will vary with model maturity, trade engagement, design completeness and programme conditions.

CTA

Coordinating MEP in a Data Center Fit Out?

Send the trade models, BIM execution plan, level datums, pour schedule and construction release date. Our team will review model maturity and confirm an appropriate coordination cycle.

✓ Federated model management✓ Rule based clash detection and issue grouping✓ Electrical room and white space coordination✓ Penetration and sleeve coordination ahead of pour✓ Clearance and maintenance access testing✓ Dedicated BIM coordinator capacity
Scroll to Top