96-Hour Construction Estimating Support | $140K Identified

Success Story · Construction Estimating · Confidential General Contractor

96-Hour Bid Support Helped a General Contractor Identify Approximately $140K in Savings

Optimar Precon supported a general contractor during an active bid when limited internal estimating capacity put the submission deadline at risk. Within 96 hours, our team reviewed the multi-trade scope, documented 14 assumptions, priced alternative scenarios, delivered quantity takeoffs in stages and identified six value engineering opportunities.

  • Confidential general contractor
  • Active multi-trade bid
  • 96-hour delivery
  • 14 assumptions recorded
  • Six VE opportunities

The client’s name, project location, project type and commercially sensitive information have been withheld. The workflow, timeline, deliverables and reported outcomes reflect information documented during the engagement.

Live bid workflow Deadline protected
96
Hours from request to final package Rolling takeoffs, clarification control and value engineering review
8:07 a.m. Initial request received
8:24 a.m. Response issued within 17 minutes
10:00 a.m. Scope breakdown underway
Friday 6:00 Final package delivered three hours early
14 Assumptions and clarifications
6 VE opportunities identified
$140K Approximate approved substitution value

Project overview

Construction Estimating Support for an Active Multi-Trade Bid

The general contractor entered the final four days of a live bid while its lead estimator was already managing two other active packages. The team needed additional production capacity without losing visibility or control of the submission.

Client Confidential general contractor
Project stage Active tender
Delivery period 96 hours
Disciplines Civil, structural, MEP, finishes and FF&E

Optimar Precon assignment

Scope Review, Quantity Takeoffs and Value Engineering Support

Through our construction estimating services , Optimar Precon extended the contractor’s preconstruction capacity while working within its existing bid-review process.

01

Scope review

Identify required trades and organise production around the fixed deadline.

02

Assumption management

Document drawing gaps instead of hiding interpretation inside the estimate.

03

Rolling takeoffs

Release completed sections early enough for contractor review.

04

Value engineering

Identify cost alternatives for assessment during the bid period.

Primary project objective

Protect the submission deadline without compromising bid visibility. The contractor needed to know what had been measured, which assumptions remained open, how undefined conditions affected pricing and which sections were ready for review.

The bid challenge

An Overloaded Estimating Team Faced a Fixed Submission Deadline

The contractor’s lead estimator was already responsible for two other live packages. Adding another multi-trade bid created immediate capacity, deadline and accuracy risks.

Risk 01

Capacity risk

The internal estimator lacked enough available hours to complete every takeoff, investigate gaps and review the package alone.

Risk 02

Deadline risk

The bid was due at 9:00 a.m. on Friday, leaving little room for delayed scope decisions.

Risk 03

Accuracy risk

Unrecorded assumptions could create omitted work, duplicated scope or unsupported pricing positions.

Scope uncertainty

Fourteen Items Required Confirmation or an Explicit Pricing Position

Optimar Precon issued one assumptions and clarification log so questions affecting scope, quantities or pricing remained visible.

14 Items recorded
11 Confirmed
3 Scenario priced
01

Identify the gap

Locate undefined or conflicting conditions in the supplied information.

02

Record the question

Identify which trade, scope or quantity the missing information could affect.

03

Request clarification

Send the item to the contractor for confirmation during the active bid.

04

Price alternatives

Quantify each reasonable interpretation when no definitive answer exists.

05

Maintain visibility

Carry the agreed allowance, condition or alternate into the package.

06

Protect bid review

Prevent uncertainty from becoming an unsupported hidden assumption.

The estimating solution

A Rolling Delivery Workflow Built Around the Contractor’s Review Process

Optimar Precon divided the estimate into prioritised trade groups and released each section when it became ready. Review began while production continued.

01

Structural and civil

Issued first to provide early visibility into major scope components.

02

MEP takeoffs

Mechanical, electrical and plumbing quantities followed during the first review.

03

Finishes and FF&E

Remaining finishes, fixtures, furniture and equipment quantities were issued afterward.

04

Final consolidation

Trade outputs, assumptions, alternatives and VE observations were combined.

96-hour delivery timeline

From Initial Request to Bid-Ready Package

The sequence connected production priorities to the contractor’s decision points. Early packages created review time while later scopes were still being developed.

  • Response issued within 17 minutes
  • Scope breakdown underway by 10:00 a.m.
  • Fourteen clarification items documented
  • Takeoffs released progressively
  • Final package delivered at 6:00 a.m.
Start

Initial request received

The request arrived at 8:07 a.m. while the bid was already active.

+17 minutes

Requirement acknowledged

Optimar Precon responded at 8:24 a.m. and began assessing the requirement.

Day 1

Scope and clarification review

The package was divided by discipline and a 14-item log was prepared.

Rolling issue

Trade takeoffs released

Structural and civil came first, followed by MEP, finishes and FF&E.

Commercial review

VE list issued

Six substitution opportunities were presented and two were approved.

Friday 6:00 a.m.

Final package delivered

The package arrived three hours before the 9:00 a.m. deadline.

Value engineering and quality control

Cost Alternatives Were Reviewed Without Removing the Contractor’s Approval Control

Value engineering was carried out alongside estimating. Each released section also passed drawing, quantity, scope, assumption and summary checks.

Value engineering review

Six Substitution Opportunities Identified During Estimating

The flag list allowed the contractor to assess alternative materials, systems or scope approaches before finalising its commercial position.

6 Opportunities flagged
2 Substitutions approved
$140K Approximate combined value
01

Drawing reference check

Confirm measurements came from the current supplied documents.

02

Quantity check

Review counts, lengths, areas, volumes and units.

03

Scope check

Compare takeoffs with trade scope and available information.

04

Assumption check

Confirm unresolved items appeared in the log or scenarios.

05

Summary check

Review trade summaries and consolidated outputs before issue.

Reported project outcomes

Structured Bid Support Increased Capacity and Protected Review Time

The engagement added estimating capacity while keeping assumptions, alternatives, package status and contractor decisions visible throughout the final bid period.

Delivery 3 hours Final package delivered before deadline The complete package arrived at 6:00 a.m. for a 9:00 a.m. submission.
Scope visibility 14 items Assumptions and clarifications recorded Eleven were confirmed and three conditions were priced through alternatives.
Approved alternatives $140K Approximate substitution value identified Two approved substitutions represented approximately $140,000 in combined package savings.

Before Optimar Precon’s support

One Estimator Was Managing Three Concurrent Bid Demands

  • Limited internal estimating availability
  • Multiple trades requiring takeoffs
  • Four days remaining before submission
  • Undefined drawing conditions
  • Review time concentrated at the end
  • VE opportunities not yet assessed

After the 96-hour delivery

The Contractor Received a Structured, Reviewable Bid-Support Package

  • Scope divided into prioritised trade packages
  • Fourteen assumptions documented
  • Alternative scenarios prepared
  • Takeoffs released progressively
  • Six VE opportunities identified
  • Final deliverables issued three hours early

Project deliverables

Bid-Support Information Prepared for Contractor Review

The final package combined measured quantities, trade summaries, assumptions, alternatives and value engineering observations.

02

Bill of materials

Material requirements consolidated from completed takeoffs.

03

Trade summary sheets

High-level summaries prepared for discipline-level review.

04

Assumptions and clarification log

Fourteen items recording confirmed and unresolved conditions.

05

Alternative scenario pricing

Separate quantity positions for three undefined conditions.

06

Value engineering summary

Six opportunities, including two approved options representing approximately $140,000.

What made delivery effective

The Bid Improved Through Structure, Not Speed Alone

Visible assumptions

Unknowns were documented rather than hidden.

Progressive review

The contractor reviewed packages while production continued.

Scenario pricing

Undefined conditions were quantified through alternatives.

Clear responsibility

The contractor retained final commercial control.

Responsibility clarification: The general contractor retained responsibility for final bid pricing, supplier and subcontractor quotations, labour rates, taxes, overheads, markups, contractual interpretation, design compliance, substitution approval and submission of the final bid. Results on other projects will vary.

Construction estimating enquiry

Facing a Bid Deadline With Limited Estimating Capacity?

Send the available drawings, specifications, addenda, scope notes, bid forms and submission deadline. Our team will review the information and confirm whether a complete or rolling estimating workflow is appropriate.

  • Multi-trade quantity takeoffs
  • Bid and tender support
  • Assumption and clarification logs
  • Alternative pricing scenarios
  • Value engineering observations